January
9th
Work begins for the new year. We still don't have our building
permits, so there's only so much that we can do. We begin pulling
down the ceiling in preparation for a new heating and airconditioning
system. |
| |
|
January 16th
Work continues pulling down the ceiling. |
|
| |
|
|
January 23rd
More ceiling work! |
| |
|
January
30th
Opening
walls
Exposing
beams
Exposing
rafters
Sheetrocking
the bathroom |
|
| |
|

|
March 27th
Yippee! We finally got the permit!
Sheet rocking and orange stripes are the theme this week. |
| |
|
April 3rd
Walls are coming down
Easter Lunch
Walls getting Spackle |

|
| |
|
 |
April 10th
Removing the floor
Hanging doors
Opening walls |
| |
|
April 17th
Opening Walls
Opening Hallways
Open Floor
Office coming together |
 |
| |
|
 |
April 24th
New Entrance Floor removed
Walls opening Up
Roof Work |
| |
|
May 22
Walls going up
Studs in place
New windows
HVAC installation |
|
| |
|
 |
May 29th
Bathroom being remodeled
New beams both above and below
New exit door
Raised platform started |
| |
|
August 14th
We're
back after a brief hiatus Getting a delivery of sand and cement block
Footing for handicap ramp
More trees down and cut
Spackled walls. Sanctuary looking good. |

|
| |
|
 |
August 28th
New handicap
ramp
New bathroom fixtures
Sanctuary with sheetrock and spackle
New entrance taking shape |